What is the “Schedule” element in gbXML?

  • Main
  • Schema
  • What is the "Schedule" element in gbXML?

The “Schedule” element is a list of schedule “sub-elements” that make up an entire calendar year. The “Schedule” element includes a child “YearSchedule” element that is a set of week schedules all assigned for a particular time period during the year defined by the begin and end date elements. These must not span more than one calendar year.

The Schedule element can be of different types including:

Temp
Fraction
OnOff
ResetTemp
ActivityLevel

The Schedule element is referenced by attributes of the Space element for purposes of assigning lighting, occupancy, and equipment schedules. For more information, click here:

http://gbxml.org/schema_doc/6.01/GreenBuildingXML_Ver6.01.html#Link18F